Default Rate Interest

Penalty or Genuine Pre-estimate of Damages?

2nd Sep 2009

Penalty or Genuine Pre-estimate of Damages?

Where the parties to a contract agree that, in the event of a breach, the contract breaker will pay the other a specified sum of money, the sum fixed may be classified by the courts either as a penalty (which is irrecoverable) or as liquidated damages (which are recoverable).

The provision will be enforceable if the sum specified represents a genuine attempt to estimate in advance the loss which the claimant would be likely to suffer in the event of a breach; it is enforceable irrespective of the loss actually suffered.
 
The purpose of the parties fixing the sum is to facilitate recovery of damages without the difficulty and expense of proving actual damage.
 
The question of whether a sum stipulated in a contract is a penalty or liquidated damages is a question of law and is to be assessed by reference to the economic conditions at the time the contract was made, not at the time of the breach. 
 
The courts have traditionally shown a reluctance to find that a clause is a penalty, particularly in the case of commercial contracts freely entered into between parties of comparable bargaining power
 
The Court of Appeal has recently affirmed this approach in the case of Taiwan Scot Co Ltd v The Masters Golf Company Limited. 
 
Taiwan had supplied golf clubs to Masters for resale in the UK. A dispute arose regarding the quality of the product and an agreement was entered into under which Masters was to make certain payments to Taiwan with a contractual interest rate of 15 per cent for late payment. 
 
Masters made smaller payments than agreed and Taiwan sued for the balance plus interest.
 
In the High Court, Taiwan was awarded the balance but was denied the contractual rate of interest on the grounds that the rate was unreasonably high and a penalty. 
 
Masters appealed the award and Taiwan cross appealed the interest decision. The Court of Appeal dismissed the appeal and allowed the cross appeal, holding that the court of first instance had been entitled to find that Masters was due to pay the balance under the contract. 
The court also held that 15 per cent was not exorbitant at the time the agreement was entered into (when interest rates were generally higher). 
 
This case suggests that commercial parties of comparable bargaining power may be able to enforce higher contractual rates of interest than are commonly included in commercial contracts (typically two or three per cent over base lending rate). 
 
Under the current credit crunch environment of ultra low rates, this may well be lower than the rate agreed in the Taiwan/Masters agreement. 
 
* David Wilson is a partner and specialist in company law at BHP Law. For more information, contact him on 0191-221 0898

Author: David Wilson, Partner (DavidW@bhplaw.co.uk)

« Back to Article List

Related Articles

Manzi Blue10th May 2010
Starting up IP issues20th Apr 2010
Tallulah Love13th Apr 2010
Incorporating a Company22nd Mar 2010
Growing your business by franchising13th Jan 2010
Incorporating a company20th Dec 2009
BHP assist company with medical product launch12th Dec 2009
Pre-Budget Report7th Dec 2009
Company info on websites20th Oct 2009
Setting up in business14th Oct 2009